Status Update - 1/24/19
January 24, 2019
| Status Item | Current Status | Previous Status | Comment |
| Schedule | red | red | Over 2 weeks delayed on build but completed 16% of stories in 2 days |
| Resources | green | green | |
| Financials | yellow | yellow | Small variance of actual vs budgeted hours due to kick-off activities |
| Quality | green | green | |
| Project Issues | yellow | red | Over 2 weeks delayed on requirement review and sign-off |
For the detailed January 24, 2019 status report, click here.